Kanban project update

Ok, we now have the flow racks in place. We have our Kanbans calculated. We have mapped the flow of the cards through the process.

Next week will be scheduling production to build our inventory stores and get them in place.

The week after that we will begin our training of our team members on the floor. We will do small group training as we begin discussing demand-based scheduling of the Kanban system. We are putting together a series of FAQ questions so we can predict the types of questions that we will receive from our team members and be prepared with a consistent response. This will help provide a unified front and immediately inject some credibility into the system.

We will cover the rules of Kanban so that bad manufacturing practices do not kill our Kanban stores. By the end of the month we hopefully will be turning on the Kanban system.